Jump to Content

Road surface drainage test rig

Testing of roadway drainage units and installations, including gutter/pavement profiles and gutter inlets (grates and side-entry inlets), has been carried out at the Mawson Lakes Campus of the University of South Australia using full-size rigs, since the mid-1970's. Early work was aimed at simulating correct surface roughness for 'hot-mix' and 'flush-seal' pavements.

In 1989 work commenced on a new full-size Test Rig : it was commissioned in 1991, and is housed indoors. It was designed to reproduce, in the laboratory, flow and hydraulic geometry/roughness conditions, which are as close as possible to those experienced in real urban roadway situations. The rig was also designed to provide minimum distortion of the roadway surface under test conditions. Its development, under the guidance of Associate Professor John Argue, was the culmination of nearly two decades of interest and work in this field of hydraulic engineering.

The Urban Water Resources Group, based at the Mawson Lakes Campus of the University of South Australia, offers this specialised consulting service using the Road Surface Drainage Rig for hydraulic testing of full-size street drainage components, such as grates, deflectors, side-entry pits, chambers with troughs etc. Any required kerb-and-gutter shape can be provided. The Rig is the only one of its kind in the Southern Hemisphere.

 


Benefits of full-size hydraulic testing


Features of the road surface drainage rig are:

Staff of the Urban Water Resources Group will be happy to assist in devising a testing or product development programme to meet your requirements.

 


Clients for whom testing has recently been carried out include:

 


Questionnaire

To assist in developing a testing program and providing a quotation for this program, we require the following information :

  1. Longitudinal slopes required, e.g. tests using longitudinal slopes 0.25%, 0.50%, 1.00%, 1.50%, 2.00%, 3.00%, 4.00%, 6.00%, 8.00%, 10.00%, 12.00%, 16.00%.
  2. 'Sag' tests : what configurations are required? e.g. single-grated chamber, twin-grated chambers, single-grated chamber with single (symmetrical) upstream troughs, etc. Are tests under 'orifice' conditions required? i.e, submerged inlet.
  3. Road pavement cross-fall slopes, e.g. 2.0%, 3.0%, 1 in 30, 1 in 40, etc. (range 0% - 5%).
  4. Kerb profile (e.g. barrier and/or mountable) - construction details required.
  5. Carriageway surface roughnesses : gutter - concrete, pavement - 'hot mix', etc.
  6. 'Depression' of inlet lip below "through" gutter invert in mm. 7. Chamber water level expressed as mm below 'through' gutter invert, if required.
  7. If inlet lip is 'depressed', what are the transition distances (upstream and downstream)? - construction details required.
  8. Test configurations : 'with grate' refers to gully trap configuration incorporating a grate; '0-grate' refers to tests conducted with grate covered, and represents the 'no grate' condition - construction details required.
  9. Inlet lintel length, particularly where different from chamber length, e.g. where upstream 'through' is used - construction details required.
  10. Flow spread limit for tests, e.g. 2.5 m, 4.0 m, etc.
  11. low test limits: - maximum flow of 250 L/s or 340 L/s - minimum percent capture, e.g. 70%, 50% etc.
  12. Are flow width versus flow curves required?
  13. Are debris (blockage) tests to be conducted? If so specify test details.
  14. What form of output is required?, e.g. curves, tabulations, curve equations etc.
  15. Are digital photographs and/or videos of tests required?
  16. When is an order for your programme likely to be placed? (Orders must usually be accompanied by a 30% deposit.)
  17. Do you require information on the 150% tax concession available to fully commercial enterprises in Australia?

Further information and answers to questions raised by the above may be directed to :

Associate Professor John Argue, on +61 8 302 3131 or

David Pezzaniti, on +61 8 302 3652 or fax +61 8 3023386


 

 

 

top^