The project will span a three-year timeline, beginning in September 2006 and ending in 2009. The timeline below shows the major milestones in the project over the next three years:
|
Month
|
2006 |
2007 |
2008 |
|||||||||||||||||||||||||||||||||||
|
Jun |
Jul |
Aug |
Sept |
Oct |
Nov |
Dec |
Jan |
Feb |
Mar |
Apr |
May |
Jun |
Jul |
Aug |
Sept |
Oct |
Nov |
Dec |
Jan-Mar |
Apr-Jun |
Jul-Sept |
Oct-Dec |
||||||||||||||||
|
Pre-recruitment preparation |
Finalising the instruments and questionnaire booklet (Jun – July 2006)
Translation of research package (Jun – Aug 2006) |
Bilingual worker training |
|
|
|
|||||||||||||||||||||||||||||||||
|
Recruitment & data collection |
|
Recruitment and data collection phase (Sept 2006 – Sept 2007) |
Qualitative field work
(Oct – Dec 2007) |
|
||||||||||||||||||||||||||||||||||
Former Yugoslavian (group 1) data collection |
Middle Eastern (group 2) data collection |
South East Asian (group 3) data collection
|
African(group 4) data collection |
|||||||||||||||||||||||||||||||||||
Group 1 recruitment |
|
Group 2 recruitment |
|
Group 3 recruitment |
|
Group 4 recruitment |
|
|||||||||||||||||||||||||||||||
|
Data entry & analysis |
|
Data entry phase (Jan – Oct 2007) |
Data analysis phase (Oct 2007 – Mar 2008) |
|
||||||||||||||||||||||||||||||||||
|
Progress reports |
|
1st progress report |
|
2nd progress report |
|
|
Final progress report |
|||||||||||||||||||||||||||||||
|
Writing & publications |
|
|
Writing & publication phase (Jan – Dec 2008) |
|||||||||||||||||||||||||||||||||||