ENTREPRENEURIAL ENTERPRISES: SP1 SUMMER SCHOOL, 2007
PROJECT PLAN FOR: Gateway to the North TEAM MEMBERS: Tessa Sharman, Foong Keng Kam, John Richards, Troy Adams
DATE PREPARED: Wed 21 Feb 2007            
             
  Week Commencing > 19 February  26 February  5 March 12 March 19 March
             
MAJOR TASK DEADLINES TO BE SUBMITTED BY:          
Individual Assignment Individuals Mon 19 Feb at 11.00pm        
Project Plan   Sharman Wed 21 Feb at 11.00pm        
Concept Statement Foong Thu 22 Feb at 11.00pm        
Project Plan Update Richards       Mon 12 Mar at 11.00pm  
Final Project Plan Adams         Mon 19 Mar at 11.00pm
Team Feasibility Report Adams         Mon 19 Mar at 11.00pm
             
WORKSHOPS   Thu 22 Feb at 11.10am Thu 1 Mar at 11.10am      
    Fri 23 Feb at 2.10pm Fri 2 Mar at 11.10am      
             
TEAM MEETINGS (Dates and times) > Wed 21 Feb at 7.30pm Mon 26 Feb at 7.30pm Mon 5 Mar at 7.30pm Mon 12 Mar at 7.30pm Mon 19 Mar at 7.30pm
TEAM MEETINGS (Dates and times) >       Sat 18 Mar at 9.00am (Celebration!)
Team meeting record (Person)  > Sharman  Foong Richards Adams/Sharman  
             
REPORT SECTION PERSON          
Concept Statement Foong, Richards (Note 1) Final: Thu 22 Feb        
Executive Summary Sharman     Draft Sun 11 Mar (Note 2) Final: Thu 15 Mar (Note 3)  
The Business Opportunity Foong, Sharman      Draft: Tue 6 Mar Final: Thu 15 Mar  
The Product/Service Richards, Adams     Draft: Thu 8 Mar Final: Thu 15 Mar  
The Target Market Sharman, Adams     Draft: Thu 8 Mar Final: Thu 15 Mar  
The Financial Plan Adams, Foong     Draft: Fri 9 Mar Final: Thu 15 Mar  
Further Factors to Consider Richards, Foong     Draft: Fri 9 Mar Final: Thu 15 Mar  
             
TASK PERSON          
Secondary data collection Foong, Richards Start: Thu 22 Feb End Tue 27 Feb      
Customer survey Team Start: Fri 23 Feb End: Sat 4 Mar      
Edit the plan Sharman, Adams       Sun 19 Mar  (Note 4)  
Note 1: The first person named is responsible for the task, and will be supported by the second person.
Note 2: Completed drafts will be circulated to all team members on the dates indicated - for discussion at the following team meeting. 
Note 3: Sections will be finalised by the team members who did each section, for final review on Sat 18 Mar
Note 4: Sections will have a final edit on Sun 19 Mar. This meeting may require all team members to be present, depending on progress on Sat 18 Mar